Baku Congress Centre

  • Laying of 35kV cable line, installation of 35 kV switchgears, 6 pieces of 2500 KVA 35/0,4kV transformers, installation of 5000A and 4000A Busbar systems, 0,4 kV Blockset panel of Jn = 5000A, 4 pieces of 1875 kVA generators, synchronous panel, metal cable channel, SCADA system, laying of 0.4 kV power cables, implementation of setup works, testing and start-up
  • Completed